Locations:
- Data in Group → Stages of Pipeline in Group
Users with the following permissions:
- Leads & Students → Change Stage from ACTIVE to NOT STARTED
Case:
If a student rejects to continue the study, the student’s stage of the pipeline in a group switches to NOT STARTED.
Problem:
Changing the stage of the pipeline in a group to NOT STARTED after the core program cancel date leads to incorrect or irrelevant records in the A/R Card.
Solution:
Added the limitation that prevents changing the stage of the pipeline in a group from ACTIVE to NOT STARTED after the core program cancel date:
There is a permission that allows overriding this limitation: Change Stage from ACTIVE to NOT STARTED (ignore Program "Cancel" Date).
Available since GEGI v4.41.0 (view release notes)